Which dependency could delay your cloud cutover?
Start with one application and the work it performs after everyone leaves for the day. A successful sign-in alone can hide a failed migration.
Find the overnight work

Which dependency could delay your cloud cutover?For a payroll workload, ask who sends the input file, when the import starts and where the results go. Include the identity running the job, its network path and any partner that limits connections by address. Name the person who can confirm that the last scheduled run finished.
Rehearse with representative data

Move an approved test copy. Run sign-in, the overnight import and the outbound report in their usual order. Compare record counts and exception logs with the source run. Measure the transfer window and note any manual step that an unattended job would miss.
Set a decision time

Work backward from the next payroll deadline. Agree when the owner must choose between continuing and returning to the original system. Record where new transactions would be reconciled if the team rolls back after writes have started.
Move one workload first
Choose a source workload, move a pilot copy and test the application from the user’s device.
A release check for the migration owner
- Baseline
- List dependencies, identities, peak work and recovery targets. Price the same demand on each option, including storage, backup, network traffic and the period of overlap.
- Rehearsal
- Move a representative copy first. Measure the slowest job, test access as a normal user and restore a file through the proposed recovery path. Record the results beside the baseline.
- Decision
- Assign an owner to approve each migration wave and another to call rollback. Give operations the alert routes, access record and first billing review date at handoff.
Further reading
Common questions
What changes the estimate for a cloud move?
Peak demand, data transfer, licensing and services that must still run on site can all change the total. Ask for the assumptions alongside the estimate.